WAC 173-340-840
General submittal requirements. Unless
otherwise specified by the department, all reports, plans,
specifications, and similar information submitted under this
chapter shall meet the following requirements:
(1) Cover letter. Include a letter describing the submittal
and specifying the desired department action or response.
(2) Number of copies. Three copies of the plan or report
shall be submitted to the department's office responsible for the
facility. The department may require additional copies to meet
public participation and interagency coordination needs.
(3) Certification. Except as otherwise provided for in RCW 18.43.130, all engineering work submitted under this chapter
shall be under the seal of a professional engineer registered
with the state of Washington.
(4) Visuals. Maps, figures, photographs, and tables to
clarify information or conclusions shall be legible. All maps,
plan sheets, drawings, and cross-sections shall meet the
following requirements:
(a) To facilitate filing and handling, be on paper no larger
than 24 x 36 inches and no smaller than 8 1/2 x 11 inches. Photo-reduced copies of plan sheets may be submitted provided at
least one full-sized copy of the photo-reduced sheets are
included in the submittal.
(b) Identify and use appropriate and consistent scales to
show all required details in sufficient clarity.
(c) Be numbered, titled, have a legend of all symbols used,
and specify drafting or origination dates.
(d) Contain a north arrow.
(e) Use United States Geological Survey datum as a basis for
all elevations.
(f) For planimetric views, show a survey grid based on
monuments established in the field and referenced to state plane
coordinates. This requirement does not apply to conceptual
diagrams or sketches when the exact location of items shown is
not needed to convey the necessary information.
(g) Where grades are to be changed, show original topography
in addition to showing the changed site topography. This
requirement does not apply to conceptual diagrams or sketches
where before and after topography is not needed to convey the
necessary information.
(h) For cross-sections, identify the location and be
cross-referenced to the appropriate planimetric view. A reduced
diagram of a cross-section location map shall be included on the
sheets with the cross-sections.
(5) Sampling data. All sampling data shall be submitted
consistent with procedures specified by the department. Unless
otherwise specified by the department, all such sampling data
shall be submitted in both printed form and an electronic form
capable of being transferred into the department's data
management system.
(6) Appendix. An appendix providing the principal
information relied upon in preparation of the submittal. This
should include, for example: A complete citation of references;
applicable raw data; a description of, or where readily
available, reference to testing and sampling procedures used;
relevant calculations; and any other information needed to
facilitate review.
[Statutory Authority: Chapter 70.105D RCW. 01-05-024 (Order
97-09A), § 173-340-840, filed 2/12/01, effective 8/15/01;