WAC 296-65-020
Notification requirements. (1) Before
any person or individual begins an asbestos project as defined
in WAC 296-62-07722 and 296-65-003 involving more than
forty-eight square feet or ten linear feet, unless the surface
area of the pipe is greater than forty-eight square feet, of
asbestos containing material, written notification must be
provided to the department. Notices must include:
(a) Name and address of the owner and contractor.
(b) Description of the facility including size, age, and
prior use of the facility.
(c) Amount of asbestos-containing material to be removed
or encapsulated.
(d) Location of the facility.
(e) Exact starting and completion dates of the asbestos
project, including shifts during which abatement work will be
accomplished. These dates must correspond to the dates
specified for asbestos removal in the contract. Any change in
these dates or work shifts must be communicated to the
department by an amended notice filed at the office where the
original notice was filed.
• When the starting date or time changes, the amended
notice must be filed no later than 5:00 p.m. on the business
day prior to the starting date in the original notice and
prior to the new starting date.
• When the completion date or time changes, the amended
notice must be filed before completion of the project, and
within eight hours from when the person learns that the change
will occur.
Notice may be filed by facsimile (fax).
(f) Nature of the project and methods used to remove or
encapsulate the material.
(2) Notices must be received by the department no later
than ten days prior to the start of the project. Notices must
be sent directly to the department of labor and industries
regional office having jurisdiction on the project.
(3) The director may waive the prenotification
requirement upon written request of an owner for large-scale,
on-going projects. In granting such a waiver, the director
will require the owner to provide prenotification if
significant changes in personnel, methodologies, equipment,
work site, or work procedures occur or are likely to occur. The director will further require annual resubmittal of such
notification.
(4) The director, upon review of an owner's reports, work
practices, or other data available as a result of inspections,
audits, or other authorized activities, may reduce the size
threshold for prenotification required by this section. Such
a change will be based on the director's determination that
significant problems in personnel, methodologies, equipment,
work site, or work procedures are creating the potential for
violations of this chapter.
(5) Emergency projects which disturb or release asbestos
into the air must be reported to the department within three
working days after commencement of the project in the manner
otherwise required under this chapter. The employees, the
employees' collective bargaining representative or employee
representative, if any, and other persons at the project area
must be notified of the emergency as soon as possible by the
person undertaking the emergency project. A notice describing
the nature of the emergency project must be clearly posted
adjacent to the work area.
(6) Incremental phasing in the conduct or design of
asbestos projects or otherwise conducting or designing
asbestos projects of a size less than the threshold exemption
specified in subsection (1) of this section, with the intent
of avoiding the notification requirements, is a violation of
this chapter.
[Statutory Authority: RCW 49.17.040, 49.17.050, 49.26.040 and 49.26.130. 99-17-026, § 296-65-020, filed 8/10/99, effective
11/10/99. Statutory Authority: RCW 49.17.040, [49.17.]050
and [49.17.]060. 96-05-056, § 296-65-020, filed 2/16/96,
effective 4/1/96. Statutory Authority: Chapter 49.17 RCW. 89-21-018 (Order 89-10), § 296-65-020, filed 10/10/89,
effective 11/24/89; 87-24-051 (Order 87-24), § 296-65-020,
filed 11/30/87. Statutory Authority: RCW 49.17.050(2) and49.17.040
. 87-10-008 (Order 87-06), § 296-65-020, filed
4/27/87. Statutory Authority: SSB 4209, 1985 c 387. 85-21-080 (Order 85-30), § 296-65-020, filed 10/22/85.]