WAC 296-104-302
Installation -- What control and limit
devices are required on automatically fired boilers after
December 1998? In addition to those requirements listed in
WAC 296-104-301, the following are also required with regard
to installations or refits of gas, oil, or combinations of gas
or oil:
(1) All boilers installed or refitted after December
1998, with fuel input ratings of less than 12,500,000 BTU/hr
which are fired by gas, oil, or a combination of gas or oil
shall comply with the fuel train requirements defined in ASME
CSD-1 (CF), as adopted in WAC 296-104-200 where applicable.
(2) Verification of fuel train compliance will be per
CSD-1. A CSD-1 report will be completed and signed by an
authorized representative of the manufacturer and/or the
installing contractor.
(3) The CSD-1 report must be made available to the
authorized inspection agency or the inspector after which a
certificate of operation may be issued. The report shall
remain in the possession of the boiler owner.
[Statutory Authority: RCW 70.79.030, 70.79.040, 70.79.150,
70.79.290, 70.79.330, and 70.79.350. 05-22-092, §
296-104-302, filed 11/1/05, effective 1/1/06. Statutory
Authority: Chapter 70.79 RCW. 04-21-069, § 296-104-302,
filed 10/19/04, effective 1/1/05.]