WAC 480-75-450
Construction specifications. Each
pipeline company must assure that any new pipeline
construction conforms to the requirements of ASME B31.4. The
longitudinal seams of connecting pipe joints must be offset by
at least two inches. In addition, the longitudinal seams must
be located on the upper half of the pipe when laid in an open
trench. Information about the ASME edition adopted and where
to obtain it are set out in WAC 480-75-999, Adoption by
reference.
[Statutory Authority: RCW 80.01.040, 80.04.060, 81.88.040. 08-12-045 (Docket PL-070974, General Order R-548), §
480-75-450, filed 5/30/08, effective 6/30/08. Statutory
Authority: RCW 80.01.040, 81.01.010, 81.88.060. 07-09-001
(Docket PL-061026, General Order R-541), § 480-75-450, filed
4/4/07, effective 5/5/07. Statutory Authority: RCW 80.01.040
and 80.04.160. 02-18-032 (Docket No. TO-000712, General Order
No. R-500), § 480-75-450, filed 8/26/02, effective 9/26/02.]