WAC 480-107-035
Project ranking procedure. (1) The
procedures and criteria the utility will use in its RFP to
evaluate and rank project proposals are subject to commission
approval.
(2) At a minimum, the ranking criteria must recognize
resource cost, market-volatility risks, demand-side resource
uncertainties, resource dispatchability, resource effect on
system operation, credit and financial risks to the utility,
the risks imposed on ratepayers, public policies regarding
resource preference adopted by Washington state or the federal
government and environmental effects including those
associated with resources that emit carbon dioxide. The
ranking criteria must recognize differences in relative
amounts of risk inherent among different technologies, fuel
sources, financing arrangements, and contract provisions. The
ranking process must complement power acquisition goals
identified in the utility's integrated resource plan.
(3) After the project proposals have been opened for
ranking, the utility must make available for public inspection
at the utility's designated place of business a summary of
each project proposal and a final ranking of all proposed
projects.
(4) The utility may reject any project proposal that does
not specify, as part of the price bid, the costs of complying
with environmental laws, rules, and regulations in effect at
the time of the bid.
(5) The utility may reject all project proposals if it
finds that no proposal adequately serves ratepayers'
interests. The commission will review, as appropriate, such a
finding together with evidence filed in support of any
acquisition in the utility's next general rate case or other
cost recovery proceeding.
(6) When the utility, the utility's subsidiary or an
affiliate submits a bid in response to an RFP, one or more
competing bidders may request the commission to appoint an
independent third party to assist commission staff in its
review of the bid. Should the commission grant such a
request, the fees charged by the independent third party will
be paid by the party or parties requesting the independent
review.
[Statutory Authority: RCW 80.01.040 and 80.04.160. 06-08-025
(Docket No. UE-030423, General Order No. R-530), §
480-107-035, filed 3/28/06, effective 4/28/06.]